Production and Maintenance Objectives
A
production plan was being used to balance development and Longwall production
to meet target outputs. The mine was production limited. These target outputs
were being used to set availability targets for the Longwall. However, it was
my impression that the engineering-maintenance department had not established
equipment life plans to achieve these availability targets. Also, I could find
no key performance indices for any area of organizational efficiency.
Maintenance Strategy—Life Plans and Preventive Schedule
An
outline life plan for the armoured faced conveyor (AFC) of the Longwall cutting
system is shown in Table 6–1 and Exhibit 6–1 shows one of the job specifications.
The
minor work of the life plan was carried out underground while the major
work(the overhaul) was undertaken off-site by contractors (or the OEM). This
was typical of most of the underground equipment.
The
minor maintenance of the equipment in the development areas was scheduled
during the week into windows of opportunity provided by production changeovers.
The work was scheduled to avoid clashes and also the weekly two shift Longwall
down-day, when minor maintenance (preventive and corrective) arising on the
Longwall was carried out. The major Longwall maintenance took place during a
Longwall change (locating it to a new production area, which took about three
weeks). Major units of Longwall equipment (e.g., the AFC, the shearer, etc.)
were held as spares common to all three collieries, which minimized Longwall
overhaul and allowed the equipment to be reconditioned off-site.
There
appeared to be no scheduled down-day for the trunk convey or and limited
maintenance was carried out on it at the weekends.
The
Engineering Superintendent was responsible for all maintenance carried out
off-site, including work specification and tendering, while the Maintenance
Superintendent was responsible for all maintenance carried out within the mine.
Observations
*
As
regards the minor maintenance work, the development and Longwall equipment life
plans were satisfactory.
*
The
major off-site maintenance work was not being carried out satisfactorily. This
was partly due to a lackof communication and understanding, concerning its
specification and quality control, among the engineering maintenance
departments.
*
The life plans for the conveyor
systems were satisfactory. However the offline preventive and corrective
workaris ing from the inspections was not being carried out. This was partly
because of the absence of a down-shift. The windows of opportunity (those
provided by shift changeovers and those occurring at the weekends) were not
being used for planned maintenance.
*
Although the colliery was production
limited the management preferred to use mid-weekdown- days for Longwall
maintenance (a 13.5% availability loss) rather than sanction overtime or
seven-day maintenance shift rostering for the weekends.