4. Preventive Maintenance Compliance
This
indicator examines the number of preventive maintenance tasks that are
scheduled compared to the number of preventive maintenance tasks completed.
Typically compiled on a weekly basis, it is useful for highlighting a
preventive maintenance program that may be developed, but not effective. In
this case, the effectiveness is hampered by failure to complete the tasks that
are scheduled. The reason for this failure may be that production is
overcommitted and will not release the equipment for maintenance, or the
maintenance resources are overcommitted on breakdowns and emergency work and,
therefore, do not have the capacity to complete the scheduled preventive
maintenance tasks.
Preventive Maintenance Tasks Completed*
Preventive Maintenance Tasks Scheduled
This
indicator takes the total number of preventive maintenance tasks completed
(usually weekly) and divides them by the total number of preventive maintenance
tasks scheduled. The result is then expressed as a percentage. Of course, the
goal is to have 100% completion of the scheduled tasks. Although this number is
not easily achieved, it should be the goal of all organizations. All preventive
maintenance tasks, including tasks performed by maintenance, operations, or
even contractors, should be factored in by this indicator.
Strengths
This
indicator effectively measures the compliance an organization has with its
preventive maintenance program. It is one of the key indicators for
any
preventive maintenance program. If the indicator is graphed weekly over a
window of six months, it can be correlated with the percentage of maintenance
activities that are breakdown or emergency. The graph will show that as
completion rate goes up, the breakdowns and emergencies go down. Conversely, as
the completion rate drops, the breakdowns and emergencies increase. If
accurately tracked, the correlation is undeniable, and can be used to gain
support for the preventive maintenance program.
Weaknesses
The
weakness highlighted is not for the indicator, but for a type of preventive
maintenance schedule that obscures or hides the fact that preventive
maintenance tasks are not completed. This is the dynamic or sliding preventive
maintenance schedule. The weakness is that the preventive maintenance task is
based on last completion date, not on a fixed schedule or a usage counter.
Therefore, if the task is not completed this month, it is not rescheduled until
it is completed. There are actually cases where monthly tasks have not been
completed for three to six months and they do not show up as late or overdue.
No organization that is truly serious about its preventive maintenance program
should ever use sliding or dynamic schedules.
5. Preventive Maintenance Estimates
Compliance
This
indicator compares the estimates of labor and materials costs for preventive
maintenance tasks with the actual costs to perform the tasks. This measure
points to the accuracy of the estimates. If the estimates are inaccurate, then adjustments
can be made so that accuracy can be insured. Accuracy is particularly vital
when the maintenance organization is using a scheduling system that is
integrated with the production scheduling system. Inaccuracies in such a system
will have dramatic negative consequences over time.
Estimated PM Task Costs*
Actual PM Task Costs
The
indicator is calculated by dividing the estimated cost by the actual cost, with
the result expressed as a percentage. A caution must be highlighted: this
indicator should not be measured over a small window of time. On occasion, it
is possible for a task to exceed the estimated cost due to exposed problems.
However, if this analysis is performed on a semi-annual or annual basis, the
results should provide a good indication of the accuracy of the estimates.
Strengths
The
strengths of this indicator include the ability to effectively monitor the
accuracy of the preventive maintenance task estimates. If the accuracy of the
individual estimates are not constantly monitored, then the overall accuracy of
the estimated labor and materials required to perform the preventive
maintenance tasks will be inaccurate, leading to budgetary problems.
Weaknesses
The
biggest weakness of this indicator is the problem of charging non-preventive
maintenance tasks to the preventive maintenance activities. For example, if a
problem uncovered during the performance of the task is corrected while
performing the task, how is the additional labor and material charge billed? If
the actual charges, which are repairs, are charged to the preventive
maintenance work order, then the estimate is exceeded and the integrity of the
estimate is in question. It is a good practice to complete the repair and then
charge the costs to a new work order written to identify the work that was
actually performed.