Three to six months later…
Try to get the project team together for a day or
two (or at least the key players from both the project side and the user side).
To prepare for this meeting, the team members involved should review the
shutdown narrative document. They should also read any lessons learned from
prior shutdowns to see whether recommended improvements were made, and if not,
why not.
Meeting minutes from the whole shutdown process
from inception to closeout should be reviewed, and one person or a small team
should be assigned to write what lessons were learned, with references to the
minutes from the status meetings and with to source documents where
appropriate.
This is a time when the team has should be rested
and reached some perspective concerning events in the shutdown. Some fundamental
issues are to be discussed here and it is essential that it not become a witch
hunt or a blame game but an authentic inquiry into what really happened, what
processes worked and didn’t work, and how could improvements be made in the
future.
At an initial meeting, discuss generally what
worked and what did not work. The report should start with an executive
summary, with the high points limited to one page.
In this meeting, discuss and make notes on:
• Did the shutdown policies
impact the shutdown for better or worse?
• In what way did the
shutdown meet or not meet the customer’s needs and expectations (and management’s
expectations) Be specific?
• Was engineering adequate
for the project?
• Were planning and
scheduling adequate for the size, complexity, and repetitive nature of the
shutdown?
• How much did the shutdown
change between the time it started and when it finished?
• How close were the budget
and the baseline schedule to the final results?
• What worked and what didn’t
work about the communications between shutdown team members, between the team
and the customer, and between the team and the contractors
• How did shutdown and
start-up of the plant go?
• What did and what did not
work in the shutdown team allocation of responsibilities. On the same subject,
were all parts of the shutdown responsibilities handled?
• What techniques or
technologies helped this shutdown (and which ones should be dropped or what
should be added in the future)
Lessons learned may also be in the following
specific areas:
-
Shutdown policies, overall evaluation of
policy team
-
Work scope, added work, emergent work
-
Team work (in and between the major teams-
planning logistics, engineering, execution, etc)
-
Job planning (in general)
-
Shutdown planning (and coordination of jobs)
-
Cost performance (how good were estimates
compared with the actuals?)
-
Work completed compared to work scheduled
-
Scheduling accuracy, completeness, compliance
-
Safety and environmental compliance
-
Contractor performance, performance of bidding
system
·
Vendor
performance, purchasing system
·
Quality,
measurement, control, management
Keep meeting minutes from this whole process and
series of meetings. Record what lessons were learned with references to the minutes
from the post shutdown meetings. Many great ideas will occur and be discussed
at these meetings and it pays to preserve them.
Chapter Headings
In the discussions, the lessons learned may come
out in several areas. Some suggested headings for these lessons (do not limit
yourself to these items) follow the phases of the shutdown itself. Specific
areas or chapter headings in the final document might be:
-
Shutdown metrics including duration,
performance to budget, jobs complete percentages, safety, and start-up.
-
Planning phase issues. How many hours did it
take to plan this shutdown
-
Execution phase issues with a focus on:
v
Safety including statistics
on accidents, near misses, and issues with permits, PPE. Include detailed
summaries of serious accidents as appendices.
v
Environmental incidents
include summaries for any serious in-cidents in the appendix.
v
Logistics Issues
v
Contractor and vendor
performance
v
Added work and emergent
work
v
Schedule compliance
including schedule breaks, logistics issues, mobile equipment issues. Any
specific items that caused delays
v
Execution and work
assignments including a review of assignments, resource issues and execution
issues
v
Close out or completion
phase issues. How did the start-up go?
Copyright 2005, Industrial
Press, Inc., New York, NY