LABOR DEPLOYMENT SCHEME
As
jobs are aligned to individuals on the Job Schedule, those individuals must be
committed to their assigned jobs within the Labor Deployment Scheme (Figure
13.6). Thereby cross-referencing resource to
assigned job.
A
master schedule template similar to that shown in Figure 13.6 should be
established for each crew or team responsible to a specific supervisor or team
leader (approximately ten people). Personnel comprising the team should be
pre-posted to the template.
Figure 13.6 Labor
Deployment
Should
any team resource have a fixed commitment to indirect activities such as
training, the pre-committed capacity should be indicated on the master template
(see employees K and L on Wednesday afternoon). Scheduling of committed
capacity to a job at a time when the resource is not available for direct
assignment is thus avoided. Such things are easily forgotten at inopportune times.
The
time periods comparable to those to which a job is scheduled are shaded
alongside the appropriate individual’s names. . This procedure minimizes the
risk of scheduling an individual to two jobs at the same time, another
situation that occurs from time to time.
Each
assignment should be cross-referenced to the appropriate job. In the interest
of conserving schedule space, reference should be to the line item number (one
or two digits), rather than the work order number (four or five digits). When
the schedule is completed, all resources available for the week should be
committed.
Figure 13.7
Complete Job Schedule
q
When
all three sections are brought together on a single form, (figure 13.7) a
complete picture is provided for the coming week that assures: Nobody is
scheduled to more than one job at any given time
q
Available
resources are fully utilized without voids or overloading
q
Internal
customers receive the promised support
When schedules are not detailed by individual,
but taken only to the level of a full load of identified work for a given team
or skill, too much work tends to be loaded for some and too little for others.
Individual team members are not clones of each other, even if they are
multi-skilled. When uneven loading is allowed to happen, the resultant schedule
is not feasible from the beginning.
Each
available mechanic should be scheduled for a full day of productive work for
each day of the schedule week. The duration should be indicated in the job
section of the schedule. In the man power deployment section, indicate
labor-hours, to avoid confusion.
q
The
majority of the crews should be scheduled for important work, which needs to be
started and completed without interruption. Make a conservative provision for
urgent schedule breaks. Assign jobs that can be interrupted or delayed, to “a
few good people” who are flexible. Flexible means that they can stop and resume
jobs, be reinstructed and reassigned to “emergencies” with minimal loss of
efficiency and without a drop in morale. Approximately 10 to 15% of scheduled
labor-hours should be on low priority jobs that can be sacrificed when
necessitated by urgent demands. Personnel assigned to such jobs are the ones to
be pulled in response to schedule breaks (urgencies).
q
Do
not schedule any job until all needs (parts, materials, tools, special
equipment, asset access, the item to be worked, any special support) are
available in the quantity required and at the time necessary.
q
List
jobs in descending order of importance until all available manhours are
committed (PMs listed first), based upon agreements reached during the weekly
coordination meeting.
q
Determine
most logical time of day to schedule PPM’s. Often, the early part of the day is
the period of heaviest breakdowns so is not a good time to schedule PM’s. On
the other hand, it is not advisable to leave them until the end of the day
because then they may not get done at all. Late morning or early afternoon are
advisable times to schedule PM’s (as shown on figure 13.7-Line Item 1)
q
Add
jobs equal to 10 or 15% of scheduled labor-hours (Line Items 21–24) as
provisional jobs to be substituted when scheduled jobs are unavoidably delayed
or completed in less than the estimated time.
q
Establish
a contingency section of the schedule (Line Items 25-27) for jobs of high
desirability, but that require equipment access not expected within the
schedule week. Should availability occur, it is more important that these jobs
be performed than some jobs on the primary schedule, but only if the
provisional jobs have been properly planned. The provisional strategy is
proactive and should be classified as schedule compliant.
q
Avoid
duplicate shutdowns by scheduling all work requiring common equipment access as
appropriate.
q
Save
minor indoor jobs for severe temperatures and inclement weather.
q
Eliminate
unnecessary trips. Look for opportunities for assignments to take advantage of
jobs in the same location, jobs using the same tools or materials, jobs needing
the same skills, and other ways to improve efficiency.
q
Schedule
multi-person jobs as the first job in the morning whenever possible so that
everyone is available to start the job at the same time.
q
When
scheduling multi-person jobs later in the day, consider previous assignments.
Don’t assign one person to a one-hour job and the helper to a two-hour job
because both will not be available to start the two-person job concurrently.
q
Think
about crew balancing delays on multi-man jobs. All four members of a crew are
seldom required for the entire duration of a job. Often another small job in
the same area can be worked con currently.
q
Allocate
people to specific jobs with supervisor’s approval. Pick the people for the
jobs based on knowledge and aptitude, required skill or equipment and on the
basis of individual training needs. Experience shows who is skillful in certain
job types and who needs more exposure to them. Balance equipment specialization
with broad facility knowledge. Utilize individual skills to the greatest extent
possible. Craftsmen should be provided with a challenging environment and the
opportunity to grow.
q
Schedules
for the forthcoming week for each supervisor’s team must be finalized and
posted prior to the end of the previous week. All preventive and predictive
maintenance inspections must be incorporated at their predetermined frequencies
and the timely completion of all identified corrective maintenance must be
scheduled.
q
Associated
“Planned Job Packages” must be delivered to and reviewed with responsible
supervisors to assure that nothing falls through the cracks due to
misinterpretation of intent or meaning. These consultations form the point at
which responsibility transitions from planner to supervisor. Nothing can be
allowed to be lost within the transition. In turn, the same level of transition
must take place between supervisor and technician at the time of assignment.
q
Operations
are to be provided with copies of schedules to confirm and document that all
agreed upon commitments are acceptable and understood by both operations and
maintenance departments.
q
It
is vital that schedules be studied and approved by everyone concerned. Approval
means that a contract has been reached between operations and maintenance to
comply with “their joint schedule” for the deployment of maintenance resources
in support of operating plans.
q
At
this point, the Weekly Master Schedule becomes a document of which all parties,
through mutual contribution, accept ownership.
q
When
urgent work is done at the expense of scheduled jobs, a schedule overload
results. A scheduled job will be displaced and carried over to the next
schedule period, unless the problem is addressed by a temporary increase in
capacity (overtime or contract labor). The displaced job is one of those
scheduled for the organization that initiates the schedule break. Therefore,
requests for schedule breaks require the sanction of the Maintenance and
Production Manager.
q
Finalize
tactics on a daily basis when the schedule is being executed. The weekly
schedule must be updated each evening during the week it is in force for the
balance of that week. While the transition from reactive to proactive
maintenance is taking place, updating will be burdensome and will have to be
performed by the planner. However, as schedule compliance matures, the required
updating becomes minimal and can be performed by the supervisor.
q
Operations
must advise planners at the earliest possible moment if they are unable to release
equipment as scheduled. Similarly, the maintenance department must advise
production management if the reverse situation is likely to occur. Planners
must ensure the coordination.
q
Planners
must keep abreast of schedule status, and detect when a job runs into trouble
before it misses a milestone.
q
Maintenance
must notify and consult with customers about any pending interruptions or
disruptions.
q
When
a job is complete, maintenance must collect the planned job package with
appropriate feedback, record the results for schedule compliance, and confirm
that the job is closed out. Feedback includes what actually happened, what
failed, and ideas for improvement.
q
Maintenance
must verify that the job was done according to the plan. When a job deviates it
is vital to learn why. Verify that the job used the materials listed in the
Bill of Material. Verify that all specialized tools and equipment were
accounted for in the plan. Verify that drawings were correct and that no
additional permits or permissions were needed. Finally, on larger or disruptive
jobs verify that all people who should have known about the job were notified
and all processes were shut down appropriately.
q
Finally,
update the planning package in all the areas mentioned.
Copyright © 2001 by Industrial Press Inc.