Work Programs consist of four sections:
q
The
top section quantifies Gross labor hours authorized each week including
budgeted overtime and contract support.
q
The
second section quantifies resources committed to various indirect activities
including vacation, absenteeism, training, meetings, etc. This sub total is
subtracted from Gross resources to calculate the resources available during a
typical week for direct work.
q
The
third section quantifies average weekly consumption of direct work resources
for response to urgent conditions such as equipment failures causing production
downtime. Included in this section are resources that must be committed to the
timely performance of PPM routines.
q
In
the fourth section, the combination of the two consumptions (urgent work and
PPM routines) are subtracted from the direct work total to quantify the weekly
resources available for relief of the backlog.
q
Within
the fifth section, the resources available for backlog relief are divided into
current levels of “Ready” and “Total” backlog to quantify backlog weeks
compared to established control limits.
This data should then be plotted on a
trend chart to trigger managerial action, as appropriate (see Figure 5.4).
Resources should be flexed (adjusted) up or down as analysis indicates
necessity. There are three resources that can be flexed:
q
Overtime
is the easiest resource to adjust, assuming that it is not already excessive.
An overtime range between 7% and 15% of paid straight time is recommended. Too
little over time is not a sound maintenance strategy. Too much over time is not
healthy, safe, or productive for either the company or the employees.
q
Contract
Support is the second most flexible strategy.
q
Permanent
Staff is the least flexible alternative, and should be chosen only when
resources and workload are out of the specified range in terms of backlog weeks
with no relief in sight, and when the condition appears to be permanent.
Figure 5.4 Backlog
Weeks Trend Chart
Business
solutions are another approach. For example manufacture of the part or process
where the excessive backlog is concentrated might be jobbed out and the machine
removed from service.
Do
not develop Work Programs only for the maintenance work force in total. This
defines the average condition. Balance must be preserved at the crew level, not
simply for the entire maintenance organization. The average condition for the
entire organization might appear to be under control only because the backlogs
of specific units, areas, skills or shifts are out of control (one or more to
the high side, with others to the low side). The result is that the workload is
not under control despite the overall adequacy of resources. Such an imbalance
is common and the phenomenon suggests that although sufficient resources exist
to get the job done, poor distribution of the available resources between the
various organizational units (crews), where the workload exists, explains why
backlog continues to grow further out of control.
Cross
training and multiple skills greatly enhance managerial ability to distribute
resources effectively.
Copyright © 2001 by Industrial Press Inc.