Organization
(a)
A centralised Engineering
Project Group (EPG), set up shortly after the 1994 audit was completed, was
headed by the Engineering Manager and three professional engineers transferred
from the colliery engineering section. Its responsibilities were:
(i)
to
procure new equipment and where necessary to assist in its installation and
commissioning;
(ii)
to
provide a project management service for capital and maintenance projects;
(iii)
to
develop standards for underground equipment overhaul and to assist in standardising
the equipment maintenance life plans (e.g., for the Longwall), and maintenance
support agreements, throughout the collieries;
(iv)
to
aid in ensuring that information (operation standards; areas of high
maintenance cost; reliability problems and solutions) on common equipment is
communicated throughout the collieries;
(v)
to
help the colliery support engineers in solving complex or technically
sophisticated problems;
(vi)
to
co-ordinate the use of equipment shared between collieries.
The
size of the group was set at a level which could deal with the core workload
(arising from responsibilities (iii) to (vi)) and was increased as necessary
(i.e., to handle responsibilities (i) and (ii)) by employing contract
engineers.
There
was a consensus among those interviewed that over the three years since the
formation of the EPG the engineering performance of the colliery equipment had
steadily improved, particularly regarding the specification and control of
quality of off-site overhauls. Projects were under way to move from ‘
buy and maintain
’ to ‘
lease
,
and
employ the OEM to maintain
.’
(b)
It appeared that the
appointment of supervisors dedicated to specific equipment had been a success.
For example, in the Longwall production group it was felt there had been a
considerable improvement, especially in the planning of the down days and of
Longwall changes.
(c)
The only change to the
resource structure had been an enlargement of the second line group (g) and
their rostering on a staggered day shift to cover the weekend work. However,
the development and production areas remained at the same levels of resource,
which were under-utilised.
(d)
The main difference between
the 1997 administrative structure and that proposed in the original audit was
that all the trade force reported directly to the shift supervisors (who were
regarded as the resource owner). To arrange resources, the equipment
supervisors had to proceed via the shift supervisors. In some cases, the
equipment supervisors had become planners and had lost touch both with the
trade force and with a knowledge of equipment condition—they spent limited time
underground.
(e)
There had been no movement
towards the longer term improvements indicated in Figure 6–10.
Strategy
(f)
The two mid-week down shifts were
still used for Longwall maintenance, even though the second line resource
worked at weekends via a staggered day shift. The reason given for this was
that the coal shearing unit, and some others, would not operate the full
fifteen shifts without maintenance (although this was done in USA mines).
(g)
There had been only a marginal
improvement in the underground equipment life plans and no improvement
whatsoever in the identification and design-out of items exhibiting low
reliability or high maintenance cost.
Recommendations – 1997
In
the light of points (b) to (e) the structure should be modified, in the short
term, to operate as indicated in Figure 6–13, this being essentially what was
recommended in 1994 but with some clarification in order to overcome the
problems identified in point (d). The first line resource should continue to
report to the shift supervisors and the second line resource to the Electrical
Supervisor and Workshop Supervisor (mechanical). These positions should,
however, be renamed Electrical Coordinator and Mechanical Coordinator. When
allocated to a downshift, both the shift resource and the second line resource
should report to the equipment supervisors responsible for that downshift
(e.g., Longwall downshift resources should report to the Longwall Supervisor on
all matters associated with the Longwall). This would be a matrix reporting
structure, and if it is to function satisfactorily the supervisors must work as
a team and link closely with the process co-ordinators—a development which, for
its success, may well call for the running of a team training exercise,
off-site and
also
involving the shift managers. It would be essential that the equipment
supervisors develop, for their own areas, improved life plans, spares lists and
information systems.
Because
of the importance of the Longwall, an inter-disciplinary team (a project
manager plus representatives from engineering, maintenance, production,
technical services and, where necessary, the operations workforce and the
tradeforce) should be formed to carry out the following tasks:
—
Identification
of the reasons for loss of cutting time and low performance. This may well be a
combination of poor maintenance, design and operation.
—
Formulation
of actions to overcome the listed problems.
—
Formulation
of a schedule for the implementation of the identified actions.
This
should be a precursor to improving plant reliability control at first level
(involving operators, tradesmen and equipment supervisors), at second level
(involving equipment supervisors and support engineers) and third level
(involving support engineers and the Central Engineering Group).
Many
of the recommendations arising from the first audit had not been carried out
because of shop floor industrial relations problems (see points (c), (d), (e)
and (f) of the re-audit review above). The management’s difficulties with
problems of this kind were understandable. However, if the company wished to
compete internationally then it was essential that these recommendations be
pursued. At the time of the re-audit, availability and cost performance were
well below international benchmarkstandar ds for underground coal mining.
FIGURE 6–13 Proposed
Administrative Structure (1997 Audit)
Copyright
© 2006 Industrial Press Inc.