1.8 THE A-B-C- ANALYSIS
The
previous discussion about RUKIs is a natural lead-in to looking at the typical
A-B-C analysis. As we have said, a few items normally account for most of the
inventory and usage of spare parts. This is best represented in Figure 1.8,
which plots cumulative usage against total inventory items. Group A items are
those items that comprise about 70 percent of the inventory value, but only 10%
of the line items; Group B, 20 percent of the value and about 20 percent of the
items; and Group C, only 10 percent of the value, but all of the remaining
items.
Clearly
the Group A items are the RUKIs. It is the management of these items that
should be the highest priority for the material management team. Several
suggestions for doing that are: 1) limit management’s effort so that it works
only on the RUKIs, 2) focus only on those RUKIs that are out-of-balance, that
is, RUKIs that have reorder points or reorder quantities higher or lower than
optimum, and 3) prioritize reporting of out-of-balance RUKIs so that the “big
hitters” are the first to be reviewed and adjusted, and the “small potatoes”
are reviewed last, if at all.
1.9 INVENTORY MANAGEMENT TECHNIQUES
Over
the last years several different techniques have been devised to improve the
availability of spare parts when needed. Let’s look at the three best:
1.9.1 Material Requirements Planning (MRP)
The
philosophy of MRP is based on the concept of determining the future time-phased
requirements for material and taking the necessary actions to insure the
material is on-hand when required. Critical path scheduling is often used to
keep the project on schedule. The key to successful MRP is the scheduling
process, which determines when certain activities are going to happen. For
example, if an overhaul of a utility turbine generator is scheduled for the
April spring outage, ordering of expected materials for the overhaul must be
backed dated from April and reflect the expected lead time to manufacture or
procure the materials. Besides overhauls, other activities that frequently use
MRP are assembly line operations and equipment preventative maintenance
procedures.
1.9.2 Distribution Requirements Planning (DRP)
DRP
is normally used in free issue situations where stocks such as fasteners,
screws, and flashlight batteries are available for maintenance to pick up
without filling out an issue ticket (just help yourself). Generally the stock
items are low cost and purchased in bulk so that precise inventory control is
not justified.
1.9.3 Non-Forecastable Requirements Planning (NRP)
NRP
is the process used when you have no idea when the material will be needed, if
at all, and you must rely on the use of risk-based processes to set stocking
levels that will meet operations availability objectives. The principal use of
NRP is the management of rarely-used items; MRP and DRP won’t work here.
Figure
1.9 summarizes what we know and don’t know about a situation when employing
MRP, DRP and NRP techniques. For all three techniques, we usually have a pretty
good idea of how many of some item will be needed. With MRP and DRP, we usually
know when it will be needed, but not with NRP. And with MRP and NRP, we usually
know why we need something; with DRP, we are not concerned with why. Because
each technique has its advantages and disadvantages, the key is to apply the
techniques where it works best.
Copyright 2005, Industrial
Press Inc., New York, NY