2.6 Reconciliation and Loss Analysis
Once
OEE is calculated, the various losses are computed from the summary sheet
information. Analyzing these losses will help you identify areas that have
major opportunity for improving OEE. Obviously, improvement in any area will
help OEE. However, the greatest opportunities for OEE improvement are those
areas with large losses.
OEE
is not the only factor behind company productivity. Therefore, the different
potential programs must be ranked for their overall benefit. For example, some
industries may have specific quality or financial considerations that must be
incorporated into their lists of priorities. All programs should not only be
evaluated for their anticipated benefits, but also be congruent with the goals
of the company. When completed, they should be measured for evidence of their
success. Evaluating the trends of most key parameters will usually identify the
impact of a program before and after its completion. Chapter 5 discusses a
value fulcrum, a concept that can help rank nearly equal projects on a reactive
to proactive scale.
When
setting goals, you should link throughput improvement with desired progress of
other parameters. Take this step when you initially assess the current
baselines of all parameters. It often takes creativity to define the
relationship between parameters. However, by clearly communicating the desired
outcomes, the priorities are understood and supported by the entire community.
I recommend that you focus on no more than three key projects at a time and
complete them as quickly as possible. Do not let your resources be diffused on
a multitude of jobs. Good progress will occur if you select and eliminate the
right limiters.
In
general, the loss analysis step is a point where synergy between OEE and other
key parameters occurs. During this step, the detailed equipment performance
records will help identify significant root cause limiters. Cross-functional
teams properly trained in objective problem solving and focused on the areas of
large losses often make breakthrough gains in OEE improvement. Detailed
observations that are provided by an effective equipment performance system
database will be of assistance. Once the key root cause limiters are identified
and eliminated, significant improvement in performance will occur.
Section
2.1 identified several types of loss that together equal total loss. These are
waste loss, speed loss, ST (stop time) operational loss, ST induced loss, and
DT (downtime) loss. Examine the example that has been used throughout this
section. Note that 4680 units were produced and 4362 units were good units. The
difference in these numbers (318 units) is the quality loss and the theoretical
factory time to produce these units is the lost time due to quality. Also, 340
minutes were used in operating at 1/2 rate (2 units/min) which results in1/2 of
this time (170 minutes) as 100 percent speed loss. Therefore the losses are as
follows:
Recall
from the previous section that OEE = 59.6 percent.
Therefore,
The
reconciliation is complete.
This
reconciliation step should be completed on a routine basis. If the OEE values
do not correlate with factory output, then the lowest value should be assumed
until the discrepancy is resolved. It takes discipline to correctly collect
data and to confirm that the database is correct. But this discipline is
necessary to be sure everyone is working with good information.
A
sample report follows (see figure 2-5). The values are filled in for the
results of the practice example. This type of form is useful when you are
looking at similar process systems and developing areas for best practices. It
is also useful for demonstrating improvement over time for the same equipment
system.
The
report displays various losses and OEE, showing that they can be reconciled to
100 percent. Also, the input for simple computation of OEE is available and can
be used to confirm that true OEE is provided. If this format is used for
monthly reports, the various OEE values can then be properly weighted relative
to Scheduled Time to determine OEE for the quarter or year. You may also want
to incorporate the number of frequencies of each category into the report. This
information is necessary and valuable in computing reliability parameters.
Reference:
1.
Nakajima, Seiichi. Introduction to TPM: Total Productive Maintenance. Cambridge, Massachusetts: Productivity Press, 1988.
Copyright 2004, Industrial
Press, Inc., New York, NY