Resistance
That which
doesn’t kill you will make you stronger
9.1 Resistance Discovered
Suppose that one of your initiatives as an internal
consultant was to work with the site personnel to develop a detailed planning
and scheduling process. The process was to focus on detailed work plans and
deciding a week in advance the planned jobs that would be executed in the
coming week. As part of the work process, you held meetings that included not
only Maintenance, but also representatives from your customer, Production. This
work took your team a considerable amount of time in order to develop all of
the details of the process and to make certain that the requirements of all
those involved were addressed. As the process was completed, you and your team
launched into the training phase; over several weeks, you trained all of the
maintenance and production personnel.
Then the much anticipated day of deployment
arrived. At first everything appeared to be functioning well. However, after
several weeks you noticed that the number of unplanned jobs was still at the
same level as before the new process was deployed. You know this couldn’t be
correct because the new process was designed to eliminate virtually all of the
unplanned work. As you investigated the problem, you discovered that the
production supervisors and their maintenance counterparts simply decided not to
follow the process. Their logic was that the work the crews were doing needed
to be done now; it couldn’t wait several weeks to go through the planning and
scheduling process. Essentially they were telling you and the work process team
that they were not going to do what was asked.
In another example, suppose that your plant deployed
a new preventative maintenance program. This new program required the mechanics
to work in a much different manner than they had in the past. Previously, they
were assigned to the production line and performed the work assigned to them by
the line operators. When these assigned tasks were completed, they returned to
their staging area and awaited a call with their next assignment. In the new
program, they were being assigned daily preventive maintenance tasks that had
to be completed to keep the program in compliance. In addition, they were
reassigned from working for Production to working for a preventive maintenance
foreman whose job it was to keep the program moving.
As an internal consultant, you were given the task
to discover why the program never was able to stay in compliance. You also had
to determine why, even with documented preventive maintenance being performed,
the equipment was still failing at the same rate as before the program was
introduced. After some investigation, you discovered that, although the
mechanics were performing the preventive maintenance tasks, they were not doing
them on a timely basis nor were they doing them very well. There lay the lack
of improvement in equipment reliability.
In another example, suppose that you and the team
have determined that having line operators do minor maintenance will help
improve equipment reliability; they will make minor repairs before the problems
become major. It also will help the productivity of the maintenance department by
having the minor repair tasks handled by the operators, leaving the maintenance
crews to work on the large, more complex ones. After the team has developed the
scope of work, purchased and distributed the tools, and trained the operators
in how to perform minor maintenance tasks, the work initiative is deployed.
Within days, it grinds to a halt because the tools that were distributed are
missing. To keep the effort moving, the project team purchases additional
tools. Once again they disappear and the work initiative falls apart. Through
sabotage of the process, the operations have caused it to fail before it is
ever allowed to get off of the ground.
In one more example, suppose you and your team
develop a process to improve materialization of the planned work. During the
training sessions, everyone agrees that this new process will vastly improve
how the maintenance jobs are materialized. However, upon deployment something
is obviously wrong. Although everyone appears to be going through the motions
associated with the new process, the foremen and planners are still making the
same number of trips to the storehouse in order to obtain job-related
materials. On the surface, the process appears to be followed, but it is
obvious that this is not actually the case. It is not being followed. Nothing
has changed in the approach towards obtaining material for the maintenance
jobs.
These four scenarios bring up a very interesting
question. Why do change initiatives developed by intelligent and caring individuals
not always succeed? You may start with a good idea. But somewhere between the
creation of the good idea and its actual implementation, the process gets
interrupted. The change, as good as it is, fails. In this chapter, we look at
why this happens and what you can do to keep change moving forward.